Supply Chain Updates

The commercial kitchen equipment industry has entered a period of extreme demand and limited supply, which is going to cause some big headaches. As your partner, we want to ensure you are aware of current conditions and advise you to order equipment well in advance to avoid delays.

News & Resources

Get the latest supply chain updates

A Look Into The Impact Of The Driver Shortage On Distributors

Restaurants aren’t the only businesses with labor problems. Distributors have their own challenges that are also driving up costs for operators. Check out this episode of the Restaurant Business podcast A Deeper Dive featuring Terry Walsh, the president of small California distribution company Southwest Traders, to discuss the

Read More

Lead times are double to triple what was typical

Equipment production that took 3 to 5 weeks in April has already climbed to as high as 3 to 4+ months. Manufacturers are seeing record order levels and at the same time are experiencing shortages in raw materials, components, and labor. Additionally, shipping demand has far surpassed current bandwidth for ports, rail and truck carriers, resulting in equipment not being produced or delivered on schedule. This affects both equipment manufactured in the U.S. and equipment imported from overseas.

Foodservice Equipment Distribution Warehouse with Forklift

Nearly all manufacturers are issuing price increases

These increases stem from cost increases in material, labor and shipping. Manufacturer price increases that usually average 2% or 3% annually are passing at 6% to 12% right now. Many factories will take two or three price increases by the end of 2021 to net an increase over 10% for the year.

What can you do?

During the next 12 months, the greatest solution Avanti can provide is to help you order in advance to avoid delays. There is a shortage of equipment that we cannot work around, we can only get ahead of.

Here’s what you can do:

  • Order equipment packages for projects as early as possible. We stage locally to your project and any extra staging cost will be smaller than the cost of not having equipment when you need it.
  • Pre-order hoods and walk-ins. These are usually custom and are needed early in a project.
  • Be flexible with manufacturer and equipment specifications—we may be able to improve a lead time by finding an alternative piece of equipment.
  • Consider stocking key equipment at a warehouse.
  • When remodeling, save what you remove, you may need it at another location in a pinch.
Avanti Project Management
Avanti Project Management
Read a letter from our president

We want to thank you for your business and partnership. We would not be here if it were not for the kitchens you create and operate. Please reach out to us if there is anything we can do to support you through these challenges.